Internal Audit Management
Introduction
Internal audits within iPassport are created using a Checklist. These checklists can be created as reusable templates within iPassport and selected when creating the internal audit.
If the preference is to produce audit reports created outside of a checklist process, then these are best stored as controlled documents with the Category of Internal Audit.
Internal audits can be on any topic; there is no limitation within iPassport on this.
| Tip |
For managers to have a quick overview of scheduled audits, the Metrics area provides a widget which lists ‘Internal Audits Due Next Month’. |
Required Permissions
There are 20 permissions associated directly with internal auditing. For convenience, they come organised by level of authority in two system roles - Audit Viewer and Audit Editor. Audit editors’ permissions include those of audit viewers.
Audit Viewer (also available in Global Viewer (excluding admin and personnel records) )
Internal Audits:Create Reports
Internal Audits:Search Internal Audits
Internal Audits:View History
Internal Audits:View Internal Audits
Internal Audits:View Non-Compliances
Internal Audits:View Print History
Desktop:Show Internal Audits Menu Item
Desktop:Show Non-Compliances Menu Item
Audit Editor (also available in Global Editor(excluding admin) )
All permissions above plus:
Internal Audits:Change OU
Internal Audits:Complete
Internal Audits:Create Internal Audits
Internal Audits:Delete Types
Internal Audits:Edit Internal Audits
Internal Audits:Edit Types
Internal Audits:Link To Records
Internal Audits:Manage Non-Compliances
Internal Audits:Manage Reviews
Internal Audits:Print Internal Audits
Internal Audits:Remove Links
Internal Audits:Schedule Reviews
Internal Audit Settings
There is currently one setting which allows closing internal audits when they still have open non-compliances. This setting is enabled (ticked) by default. When it is not enabled (ticked), all related noncompliances must be closed before the internal audit can be set as completed.
The setting can be adjusted independently for each OU by navigating to Administration > Settings > Organisational Unit Preferences, selecting the OU and clicking, Internal Audit Settings. Once the option, “Allow closing Internal Audits with open non compliances” has been ticked or unticked, click Save.

Creating Internal Audits
Creating a new internal audit record
| Note |
Note: Checklists should be in place before they are used in internal audits. |
The Internal Audits menu item is located under the Quality Management main menu item.

To create a new internal audit:
- Go to Quality Management > Internal Audits > New Internal Audit (or use the [+] sign shortcut)
- In the New Internal Audit Step 1 of 3 screen, enter values for the following fields (at least those marked required must be entered to continue)-
- Organisational Unit - this provides the internal audit with a ‘home’ and helps define who can and cannot access the record
- Name (Required) - this field is displayed in search results so it’s beneficial to make it descriptive; the system will issue a warning if the name has already been used and it will prevent advancing to the next step.
- Type - this allows breaking Internal Audits down by a searchable and reportable type. Only one type of internal audit can be selected/assigned from the dropdown menu. New types can be added using the spanner icon to the right of the field (please refer to, Adding New Types below).
- Index (Required) - it can be left to Auto Generate by iPassport and it will use the settings in the Administration area; or it can be entered manually by clicking the cog icon, which toggles the auto generate on and off. The index is only used as an authentication method to help ensure there is a unique identifier for the record, therefore it can be manually configured. The system will issue a warning if the index has already been used and it will prevent advancing to the next step.
- Schedule On (Required) - this field allows setting the date the audit is intended to happen. Internal audits can be created in advance so that an audit calendar can be built up well in advance. The schedule on date can be adjusted at any point until the internal audit is completed.
- Frequency (months) - this field allows making internal audits recurring, when desirable; by setting a frequency in months (only whole numbers are accepted), a new audit will be automatically created when the current one is marked as complete. More detail is available below.
- Completion Due On - allows setting a deadline by which the internal audit must be completed
- Authors - to record the people who prepare the audit
- Locations - this helps to further categorise the record
- Auditor - this is a free text field which simply allows writing the name of the auditor; it is currently not linked to a contact record in iPassport so no reminders are triggered from this field.
- Verifier - a verification step will only be added if a user is added to this field; if a user is selected from the dropdown menu (which displays names that match the text entered), this person will be assigned a task to verify the internal audit and confirm dates for the next audit when it’s recursive. Please find further details below.
- Introduction and Scope - this field is available to provide background about the audit
Note: Should a reminder of the audit be required, the best solution is to create a task and assign it to the auditor. If the audit is not for a few months time, the task can be created with an appropriate Activation Date set in the future.
- Click Next Page

- In the New Internal Audit Step 2 of 3 screen (Peer Review Step), optionally enter values for the following fields-
Note The peer review step is used to request other staff members’ feedback on the design of the audit. If this is not required the step can be skipped.
If filled, a task is issued to the selected users when the audit has been created, dependant on the Tasks Active on date.- Review to be completed by - to set a date by which the peer review should be completed
- Tasks active on - to set a date to release the tasks in the future if preparation time is needed before the audit can be reviewed
- Reviewers (Distribution Lists) - to select a group of reviewers in ‘bulk’ by selecting existing Distribution List(s); only distribution lists of type Reviewer are listed
- Reviewers (Users) - to select individual users one by one
- Priority for review tasks - to select a level of urgency from the dropdown menu
- Task Description - iPassport pre-populates the field with a standard message which can be edited and extended as required
- Click Next Page

- In the New Internal Audit Step 3 of 3 screen, select one or more existing checklists to be used for this audit
Note It is not required to select a checklist at this point and an internal audit can be completed without use of a checklist. However, internal audits are designed to use checklists for a more effective and efficient process. So, if it is missed here (for example, it has not been written yet), it can be added from the Checklist tab within the internal audit record later.
IMPORTANT: When a Checklist is selected for an audit, the system makes a copy of the checklist in its current state, so changes made to the checklist after this point will not be reflected in the internal audit.
If needed, the checklist can be removed and added again, once an audit is scheduled, but this is only possible while none of the steps in that checklist have been marked yet. Removing one section of a checklist also removes all the other sections of the same checklist; a warning is shown before this happens. A checklist with no sections or steps cannot be added to an audit.
- Click Create Audit
Adding New Types
To add new types of audits:
- Open an incomplete internal audit
- Click the edit (pencil) icon next to the Type field
- Click the manage (spanner) icon that appears
- Click [+]Add Audit Type in the Audit Types pop-up window to open the Create Audit Type section
- Enter a name for the new audit type in the Name field
- Click Create Audit Type
- Use the delete (trash/bin) and edit (pencil) icons to manage the types listed below
NOTE: Only types not in use can be deleted

Searching Internal Audits
All internal audits are listed under the Search Internal Audits tab. A set of search filters help locating any internal audit quickly. To save screen space, some search filters are kept hidden and can be easily viewed by clicking the Advanced Search bar.

To find an internal audit:
- Go to Quality Management > Internal Audits > Search Internal Audits
- Use the following filters to narrow down the search -
- Search - free text can be entered to look for audits by name or index
- OU - a dropdown menu displays all Organisational Units where the user has permission to view internal audits; ability to view internal audits is limited to the OUs where the permission (Internal Audits:View Internal Audits) is granted
- Type - user created ’types’ help classify and locate audits
- Status - the options are, Not Started, In Progress, Completed and Overdue; leave the field blank to view all statuses
Note Only the status label, Overdue is tagged to an audit’s name in red.
- Review Status - if review feedback is requested for an audit, it can be in one of the following statuses, Reviewed, Scheduled, Under Review or No Reviews; leave the field blank to view all statuses
Note An audit might have already been reviewed and have reviews underway at the same time. These are marked with both tags:

- Date - is after - is before - the Date field offers the options, Created, Schedule on or Completion Due; the other two fields have pop-up calendars to set a range for the date parameter
- Search - free text can be entered to look for audits by name or index
Exporting Search Results
The list of audits resulting from any search can be exported in CSV format by clicking Export CSV, in the top right corner of the results section.
Viewing the Internal Audit Record
Once the internal audit is created, it can wait there until the audit needs to be performed. It is also possible to adjust the Scheduled On date at this point if needed. The Scheduled On date can’t be after the Completion Due On date; the system will validate this when these fields are edited.

The first three tabs of the record reflect the steps used to create it. The General tab, which the record opens to by default, represents the first step (page) when creating the internal audit. The Reviews tab and the Checklist tab represent the other two steps in the creation process.
Most elements of the record can be edited through these tabs while the audit is incomplete.
The Organisational Unit (OU) is the exception. To change it, the permission, “Internal Audits:Change OU” is required for the option, ‘Change OU’ to become available in the Actions dropdown menu.
It is possible to move an internal audit to a different OU after it has been closed, provided the user also has the permission, “Internal Audits:Complete”.
Non-compliances are created as part of the internal audit, based on the checklists chosen. As such, it is not possible to create a noncompliance from the Non-Compliances tab; it simply shows ones created from the Checklist tab as part of the audit.
The other tabs work in the same way as they do elsewhere in the system.
Performing the internal audit
When the internal audit record has been created it is possible to ‘perform’ the audit, using the Checklists tab in the record. The Checklists tab shows the checklist(s) loaded to the internal audit and by working through them, the audit can be completed.
An audit with the status Not Started can be moved to In Progress by selecting Set as In progress from the Actions dropdown menu; this requires the permission, “Internal Audits:Edit Internal Audits”.
To perform the audit:
- Open the internal audit by going to Quality Management > Internal Audits > Search Internal Audits
- Click the Checklists tab to open it

- Click the magnifying glass in the Actions column of a checklist to access its elements

- Mark off each item of the checklist by selecting one of the options in the Actions column; from left to right these options are:
- Compliant (’✓ ’ check) - marking an item as compliant opens a pop-up window to provide evidence. Free text can be entered here and other evidence such as a picture or scans, can be added by dragging them into the dotted rectangle marked, Click here to attach evidence or by clicking inside the dotted area to open a ‘search and select’ browser window. Other records in iPassport can be linked at the bottom of the pop-up window. Click the button, “Mark As Compliant” to complete the approval or click the “X” in the top right corner to close it without marking the step as compliant.

- Noncompliant (’X’ cross) - marking an item as noncompliant opens a noncompliance pop-up window where some of the key information can be entered.
Critically, a noncompliance record is created from this information, allowing the noncompliance to be expanded and actioned. Immediate and follow up actions are not created at the time of recording the noncompliance but through the (now) linked noncompliance record. The noncompliance record can be accessed from the Non-Compliances tab in the internal audit, or from the noncompliant audit step itself.Note A noncompliant internal audit checklist step and its associated noncompliance are two distinct items and once created they can have attachments and links added separately.
Non-Compliances created from an internal audit checklist step (also referred to as a ‘requirement’), will display information about their origin in the internal audit, with details about attachments and links added there.
- Not Applicable (’-’ dash) - marking an item as not applicable opens a pop-up window where observations, attachments and links can be added. Click the button, “Mark As Not Applicable” to complete the process or click the “X” in the top right corner to close the pop-up window without changing the state of the step.

- Compliant (’✓ ’ check) - marking an item as compliant opens a pop-up window to provide evidence. Free text can be entered here and other evidence such as a picture or scans, can be added by dragging them into the dotted rectangle marked, Click here to attach evidence or by clicking inside the dotted area to open a ‘search and select’ browser window. Other records in iPassport can be linked at the bottom of the pop-up window. Click the button, “Mark As Compliant” to complete the approval or click the “X” in the top right corner to close it without marking the step as compliant.
| Note |
Any attachments added are listed near the bottom of the lightboxes that open when clicking Compliant (✓), Not Applicable (-) or, when clicking the magnifying glass icon (?) which shows once a step has been marked. Steps can be revisited to upload, remove or replace more evidence. It’s possible to open these lightboxes just to manage attachments and then click the “X” in the top right corner to close them without altering the state of the step. For more information on the attachment icons, please refer to the user guide, Attachment Management.![]() |
Completing the internal audit
Once the checklist items have been worked through, the internal audit can be marked as complete. For the internal audit to be marked as complete, not all the noncompliances have to be closed if the Organisational Unit Preference, “Allow closing Internal Audits with open non compliances” has been enabled. Please see the settings section above. If there are open noncompliances, they’ll remain linked to the internal audit as separate records.
If the audit still has open peer review tasks, these are invalidated when the audit is completed (or sent for verification). A confirmation message warns how many open reviews will be invalidated before you continue.
To mark an internal audit as complete:
- Expand the Actions drop down menu and select the Set as Completed option (this requires the permission, “Internal Audits:Complete”)

- Click the Go button and the internal audit should be marked as complete/finished
If a Verifier has been set on the audit, it is not marked as complete at this point. Instead, the pop-up shows the message, “Before this audit can be closed it needs to be verified by” followed by the verifier’s name, and the button reads Request Verification. Clicking it moves the audit to the Awaiting Verification state; it is only marked as complete once the verifier has verified it (see Verification Step below).
[[SCREENSHOT NEEDED: Set as Completed pop-up for an internal audit with a Verifier set, showing the “Before this audit can be closed it needs to be verified by …” message and the Request Verification button]]
The fields under the general tab will still be editable after it’s completed. It will still be possible to manage the evidence submitted but it won’t be possible to change the state of any steps.
Verification Step
When a verifier is appointed in the field provided, the system automatically assigns a task to this person when the audit is set as completed (by clicking Request Verification), and the audit moves to the Awaiting Verification state. A task will be created even if the verifier is the same person who completes the audit. The task will appear in the sidebar like any task and clicking it will take the user to the record so it can be verified easily.
When the verifier verifies the audit, it is marked as Completed and, for a recurring audit, the next audit is created. The verifier can instead reject the verification; this is recorded as “Verification Rejected” and the audit returns to In Progress.

| NOTE - Transferring a Verification task |
|---|
Verification requests generate a task for the assigned verifier. If verification of an internal audit needs to be transferred to another user, the task must be reassigned manually. Updating the Verifier field does not automatically reassign the associated task. To reassign the task, open the Tasks tab within the audit record and click the pencil icon next to the Assigned To field. Select the new assignee and save your changes. |
Recurring Internal Audits
All scheduled internal audits will be posted in the 'Internal Audit Schedule' tab and if they are recurring audits, they will be automatically added upon completion of the previous one (or, where a verifier has been set, once the previous one has been verified). The audits are listed in order of their completion due date, with the earliest appearing at the top. They can be filtered by 'Open' or already 'Completed'.
If a value is entered in the Frequency field, the internal audit will automatically become recurring. At the point of completing the internal audit, a pop-up window allows adjusting the dates calculated by the system. The “Schedule the next audit on” date is worked out from the day the audit is completed plus the frequency value. The “Next audit’s Completion due date”, is set one month after the suggested “Schedule the next audit on” date.
If these dates are adjusted, the due date can't be earlier than the scheduled date.

If a verification step has been added, the verifier will also have an opportunity to edit these dates when performing the step.

| Note |
| Please check that the dates are in chronological order. If the completion date is set before the scheduled date, the system won't allow verifying an internal audit. |
A new copy of the internal audit will be created with the approved dates, and it will be listed under the 'Internal Audit Schedule' tab. It will include the same checklist(s) as the original audit, but it will take a fresh copy of the latest version of the checklist(s). If a checklist is updated after this, the changes won't be reflected in the audit. It must be removed and added again when required.
The new audit is not an exact copy of the original. Its name has “on” and the new scheduled date added to the end (replacing any date added in this way previously), and it is given a new auto-generated index. The Authors are carried over, but the Locations and peer reviewers are not copied.
Inactivated checklists
Setting a checklist as inactive only stops it being offered when adding a checklist to an audit. It does not affect audits that already use it, so they can still be completed, and a recurring audit will keep carrying it forward into each new audit. Unfortunately, nothing on the audit shows that a checklist is inactive. At the moment the only way to deal with this is the same as above: remove it from the scheduled audit and add a replacement.
Re-opening an Internal Audit
It is also possible to reopen an internal audit once it has been completed. The Actions dropdown menu will include the option, “Re-open” in completed audits. This option is only visible to users with both the permissions, “Internal Audits:Edit Internal Audits” and “Internal Audits:Complete”. A confirmation message, “Are you sure you want to reopen this completed internal audit?”, is shown first. Completing this action reverts the internal audit to the status, “In Progress” and leaves an entry in the Changelog tab for future reference.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article